Connect with us
Advertisement

Lucara splashed over P570 million on Karowe underground project

Top gem junior miner Lucara Diamond Corp is investing heavily on the expansion of its Karowe Mine. So far, the Canadian headquartered multi-listed miner has spent over P570 million on the project that will transform Karowe into a world-class underground mine.

In an update on Wednesday, Lucara said the Karowe underground project is in a fully financed position with the funds to be provided from the $220 million senior debt facilities package (the over P2. 4 billion announced on the 12th of July 2021).

Additional funds are also expected to come from the recently closed equity financing of C$41.4 million (over P330 million), and the projected cash flows from the Karowe open pit mine, during the underground construction period.

Although COVID-19 related delays have impacted the original schedule, Lucara says no material variances between the 2019 feasibility study and current project design have resulted following the completion of detailed design and engineering work undertaken in 2020 and 2021.

Total capital expenditures, including contingency have, however, increased marginally by approximately 4%, to $534 million (P5.9 billion), due to the increase in the production shaft diameter and additional mine development.

The Karowe underground project is planned to extend the mine life to at least 2040 mining predominately from the highest value EM/PK(S) unit, and is forecasted to contribute approximately $4 billion(over P40 billion) in additional revenues, using conservative diamond prices, starting in 2026.

So far $51.4 million(over P573 million) has been spent to date out of the total budget, primarily on engineering and procurement of long lead items. Lucara says this year alone a total of $120 million (over P1.2 billion) will be spent on the project.

From beginning of 2020 till June 2021 all critical path items were addressed, and a concerted effort was placed on detailed design, engineering and procurement which have helped to significantly de-risk the project.

The P573 million spent on the project to date, includes amongst others on shaft and geotechnical engineering, procurement of long lead time and essential shaft sinking items, surface infrastructure and construction activities, bulk power supply power line engineering and procurement.

Mobilization of the shaft pre-sink team commenced in late Q2 2021 with shaft pre-sinking on track to commence in mid Q3 2021. Open pit mining operations have been adjusted to limit the risk of production shortfalls during the ramp up of the Underground mine operations commencing in H1 2026.

The Karowe Mine is an existing conventional drill and blast open pit operation, with diesel excavators and trucks providing an average annual 2.6 million tonnes of kimberlite feed to the mill. The open pit mine operation is expected to terminate mid-2026, ending at an elevation of approximately 700 metres above sea level (masl).

The Underground project is targeting the substantial resources remaining below the economic extents of the open pit in the South Lobe. A 7,200 tonne per day shaft operation utilizing long hole shrinkage (LHS) mining will provide an additional 13 years of mine life to the Karowe operation after a five-year construction period.

The mine will be accessed from a 767-metre deep production shaft, 8.5 metres in diameter, driven from surface and will be equipped with two 21- tonne skips for production hoisting and a service cage for man and material movement through the mine.

This shaft will also serve as the main fresh air intake to the mine. A second shaft, 6.0 metres in diameter, driven 733 metres deep from surface, will form the main ventilation exhaust pathway. The LHS method is planned to systematically drill and blast the entire lobe on a vertical retreat basis.

In LHS, a significant proportion of the blasted muck is left in the stope during blasting and stoping to stabilize the host rock, with only the swell extracted during the drill and blast phase. Mucking will take place from draw points from the 310L (310 masl) extraction level. Once the column is fully blasted, the stope will be drawn empty by mucking the draw points.

The bottom-up approach of the LHS mining method takes advantage of the higher value EM/PK(S) kimberlite unit at depth in the South Lobe at Karowe, and balances high initial capital costs with low operating costs while de-risking the project with respect to the geotechnical and hydrogeological aspects of the host rocks.

Furthermore, there will be parallel pre-sinking of shafts, ventilation fans and coolers to be located on surface, in shaft grouting of water strikes changed from grout curtain installation from surface, planned development of an additional sublevel to assist in drilling of drawbells.

Civil works for the underground expansion progressed through detailed design, and construction activities ramped up through Q1 2021 with completion of the construction area terraces, laydown areas, shaft pad preparations, along with commencement of shaft collar box cut construction and blasting within the shaft columns in preparation of civil works.

Hoist houses, hoist foundations and shaft collars are now well advanced and on time for commencement of pre-sinking which is planned during Q3 2021. To date, over 430 days have been worked LTI-free, on the project. Temporary power for shaft sinking is required until such time as the upgrade bulk power supply infrastructure is commissioned in Q4 2022. A three phased ramp up of the generator capacity is planned to support the increasing power requirements related to the shaft sinking activities.

A power supply and services contract for the temporary generators has been signed with Aggreko International Projects Limited. Mobilization has been initiated with the generator pad established. Commissioning of Phase 1 is scheduled during Q3 2021 to support the start of pre-sink activities.

Bulk Power Supply During 2020, Lucara negotiated and signed a self-build agreement with the Botswana Power Corporation (BPC) for the construction of two substations and a 29 km long 132kv Transmission line from BPCs newly established Letlhakane substation to the Karowe mine.

The planned route follows an existing regional 400kV line and then runs parallel to the existing 11kV transmission line currently supplying bulk power to the Karowe mine. The new power infrastructure will provide the required power for the current open pit, processing plant and the underground mine expansion. Commissioning of and handover to BPC is scheduled for Q4 2022. Construction of substations is scheduled to commence in Q3 2021 and power line construction in Q1 2022.

Next steps on the Karowe Underground development will include mobilization to site and start of pre-sink in Q3 2021, completion of early civil works in Q4 2021, continuation of detailed design and engineering of the underground mine infrastructure and layout, commencement of bulk power supply infrastructure with substation construction scheduled to start in Q3 2021, and transmission line engineering in H2 2021.

Lucara President and Chief Executive Officer, Eira Thomas, said the company has made tremendous progress on the Karowe underground expansion project over the last eighteen months, despite the challenges imposed by the global pandemic.

This project comes at a time when the outlook for the diamond market is stronger than it has been for many years representing an exciting growth opportunity for our shareholders and stakeholders in Botswana, she said on Wednesday.

Business

New Khoemacau owners commit to mine’s multibillion Pula expansion

6th December 2023

The future of Botswana’s largest copper and silver operation, Khoemacau Copper Mining, looks promising as the new owners, MMG Group, commit to the mine’s expansion plans. MMG, an Australian headquartered company owned by China, has expressed its dedication to doubling Khoemacau’s production and transforming it into one of the most significant high-grade copper operations in Africa.

Nan Wang, the Executive General Manager for Australia and Africa at MMG, stated that while the immediate focus is on maintaining a consistent production level of 60ktpa, there are solid plans to increase Khoemacau’s production capacity. The company aims to double its production from 3.65Mtpa to 8.15Mtpa, resulting in an increase in payable copper from approximately 60ktpa to around 130ktpa.

To achieve this expansion, Khoemacau has completed a pre-feasibility study on the project and a solar power initiative. The next step is to conduct a feasibility study, which will pave the way for increased production capacity. Additionally, Khoemacau has identified extensive exploration opportunities across its license area, positioning the company for an exciting new phase of development.

The current Khoemacau operation reached full production and nameplate capacity in December 2022, following over a decade of investment totaling over P10 billion. This significant investment allowed for an intense exploration program, resulting in the development of the most automated underground mining operation in Botswana. The first concentrate was produced in June 2021, and the product entered the export market in July of the same year. Throughout 2022, the company has been working on the pre-feasibility study for the expansion project, with the feasibility study scheduled for the following year.

The expansion plans will involve the construction of a new world-class process plant in Zone 5, where the current mining of ore takes place. This new plant will be larger than the existing one in Boseto, which currently receives ore from Zone 5. The expansion will also involve the development of new underground mines, including Mango, Zone 5 North, and Zeta North East. These additional mines will bring the total number of underground shafts at Khoemacau to six. The ramp-up of production from the expansion is expected to occur in 2026.

Khoemacau, which acquired assets in the Kalahari Copper Belt after the liquidation of Discovery Metals in 2015, currently employs over 1500 people, with the majority being Batswana. The Khoemacau Mine is located in north-west Botswana, in the emerging Kalahari Copperbelt. It boasts the 10th largest African Copper Mineral Resource by total contained copper metal and is one of the largest copper sedimentary systems in the world outside of the Central African Copperbelt.

The mine utilizes underground long hole stoping as its mining method and conventional sulphide flotation for processing. Resource drilling results have shown the existing resources to have continuity at depth, and there are several exploration targets within the tenement package that have the potential to extend the mine’s life or increase productivity.

The Zone 5 mine has already ramped up production, and further expansion in the next five years will be supported by the deposits in the Zone 5 Group. The estimated mine life is a minimum of 20 years, with the potential to extend beyond 30 years by tapping into other deposits within the tenement package.

In conclusion, the commitment of MMG Group to Khoemacau’s expansion plans signifies a bright future for Botswana’s largest copper and silver operation. With the completion of pre-feasibility and feasibility studies, as well as significant investments, Khoemacau is poised to become one of Africa’s most important high-grade copper operations. The expansion project will not only increase production capacity but also create new job opportunities and contribute to the economic growth of Botswana.

 

Continue Reading

Business

Khoemacau Copper Mining to be acquired by MMG Limited

6th December 2023

Khoemacau Copper Mining, a leading copper mining company, has recently announced its acquisition by MMG Limited, a global resources company based in Australia. This acquisition marks a significant milestone for both companies and demonstrates their commitment to continued investment, growth, and sustainability in the mining industry.

MMG Limited is a renowned mining company that operates copper and other base metals projects across four continents. With its headquarters in Melbourne, Australia, MMG has a strong track record in mining and exploration. The company currently operates several successful mines, including the Dugald River zinc mine and the Rosebery polymetallic mine in Australia, the Kinsevere copper mine in the Democratic Republic of Congo, and the Las Bambas Mine in Peru. MMG’s extensive experience and expertise in mining operations make it an ideal partner for Khoemacau.

MMG’s commitment to sustainability aligns perfectly with Khoemacau’s values and priorities. Khoemacau has always placed a strong emphasis on safety, health, community, and the environment. MMG shares this commitment and applies the principles of good corporate governance as set out in the Corporate Governance Code of the Hong Kong Listing Rules. As a member of the International Council on Mining and Metals (ICMM), MMG adheres to sustainable mining principles, ensuring responsible and ethical practices in all its operations.

Over the past 12 years, Khoemacau’s current shareholders have made significant investments in the development of the company. With approximately US$1 billion deployed in the project, Khoemacau has successfully transformed from an exploration and discovery phase to a fully-fledged operating copper mine. The completion of the ramp-up of the Zone 5/Boseto operations has set the stage for the next phase of expansion.

With the acquisition by MMG, Khoemacau is poised for an exciting new chapter in its development. The completion of a pre-feasibility study on the Khoemacau expansion and a solar power project has paved the way for increased production capacity. The feasibility study will be the next step in doubling the production capacity from 3.65 million tonnes per annum (Mtpa) to 8.15 Mtpa, resulting in a significant increase in payable copper from approximately 60,000 tonnes per annum (ktpa) to 130,000 ktpa. Additionally, Khoemacau has extensive exploration opportunities across its license area, further enhancing its growth potential.

The CEO of Khoemacau, Johan Ferreira, expressed his gratitude to the current owners for their stewardship of the company and their successful transformation of Khoemacau into a fully operational copper mine. He also highlighted the company’s focus on the expansion study and its vision for the future with MMG. Ferreira emphasized that the partnership with MMG will ensure Khoemacau’s long-term success, delivering employment, community benefits, and economic development in Botswana.

MMG Chairman, Jiqing Xu, echoed Ferreira’s sentiments, stating that the acquisition of Khoemacau aligns with MMG’s growth strategy and vision. Xu emphasized MMG’s commitment to creating opportunities for all stakeholders, including shareholders, employees, and communities. He expressed confidence in Khoemacau’s expansion potential and the company’s ability to realize its full potential with the support of MMG.

The sale of Khoemacau to MMG is subject to certain conditions precedent and approvals, with the expected closing date in the first half of 2024. This acquisition represents a significant step forward for both companies and reinforces their commitment to sustainable mining practices, responsible resource development, and long-term growth in the mining industry.

In conclusion, the acquisition of Khoemacau Copper Mining by MMG Limited signifies a new era of investment, growth, and sustainability in the mining industry. With MMG’s extensive experience and commitment to responsible mining practices, Khoemacau is well-positioned for future success. The partnership between the two companies will not only drive economic development but also ensure the safety and well-being of employees, benefit local communities, and contribute to the overall growth of Botswana’s mining sector.

 

 

Continue Reading

Business

BPC Signs PPA with Sekaname Energy

6th December 2023

The Botswana Power Corporation (BPC) has taken a significant step towards diversifying its energy mix by signing a power purchase agreement with Sekaname Energy for the production of power from coal bed methane in Mmashoro village. This agreement marks a major milestone for the energy sector in Botswana as the country transitions from a coal-fired power generation system to a new energy mix comprising coal, gas, solar, and wind.

The CEO of BPC, David Kgoboko, explained that the Power Purchase Agreement is for a 6MW coal bed methane proof of concept project to be developed around Mmashoro village. This project aligns with BPC’s strategic initiatives to increase the proportion of low-carbon power generation sources and renewable energy in the energy mix. The use of coal bed methane for power generation is an exciting development as it provides a hybrid solution with non-dispatchable sources of generation like solar PV. Without flexible base-load generation, the deployment of non-dispatchable solar PV generation would be limited.

Kgoboko emphasized that BPC is committed to enabling the development of a gas supply industry in Botswana. Sekaname Energy, along with other players in the coal bed methane exploration business, is a key and strategic partner for BPC. The successful development of a gas supply industry will enable the realization of a secure and sustainable energy mix for the country.

The Minister of Minerals & Energy, Lefoko Moagi, expressed his support for the initiative by the private sector to develop a gas industry in Botswana. The country has abundant coal reserves, and the government fully supports the commercial extraction of coal bed methane gas for power generation. The government guarantees that BPC will purchase the generated electricity at reasonable tariffs, providing cash flow to the developers and enabling them to raise equity and debt funding for gas extraction development.

Moagi highlighted the benefits of developing a gas supply industry, including diversified primary energy sources, economic diversification, import substitution, and employment creation. He commended Sekaname Energy for undertaking a pilot project to prove the commercial viability of extracting coal bed methane for power generation. If successful, this initiative would unlock the potential of a gas production industry in Botswana.

Sekaname Energy CEO, Peter Mmusi, emphasized the multiple uses of natural gas and its potential to uplift Botswana’s economy. In addition to power generation, natural gas can be used for gas-to-liquids, compressed natural gas, and fertilizer production. Mmusi revealed that Sekaname has already invested $57 million in exploration and infrastructure throughout its resource area. The company plans to spend another $10-15 million for the initial 6MW project and aims to invest over $500 million in the future for a 90MW power plant. Sekaname’s goal is to assist BPC in becoming a net exporter of power within the region and to contribute to Botswana’s transition to cleaner energy production.

In conclusion, the power purchase agreement between BPC and Sekaname Energy for the production of power from coal bed methane in Mmashoro village is a significant step towards diversifying Botswana’s energy mix. This project aligns with BPC’s strategic initiatives to increase the proportion of low-carbon power generation sources and renewable energy. The government’s support for the development of a gas supply industry and the commercial extraction of coal bed methane will bring numerous benefits to the country, including economic diversification, import substitution, and employment creation. With the potential to become a net exporter of power and a cleaner energy producer, Botswana is poised to make significant strides in its energy sector.

Continue Reading