Connect with us
Advertisement

P500 million Tshesebe-Masunga road dispute lands in Court

500-Million-Tshesebe-Masunga-road-on-a-stand-still

The Tshesebe-Mosojane-Masunga road estimated costs stand at P500 million, the tender which was awarded to Bash Carriers in 2017 has not taken shape four years after the project was commissioned.

Tshesebe-Mosojane-Masunga road when it was commissioned, was estimated at P500 million in value, this included construction of 22.50km of the two lane carriage way and 28.70km of access roads including associated bridge works, cross drainage works, storm water drainage works and relocation of services.

When it was first tendered the contract was awarded to Bash Couriers but was terminated after it was alleged that the contractor failed to deliver. It was said that Bash Couriers Construction Company was lagging behind schedule.

This publication visited the sites of Tshesebe-Masunga road last year December and it was evident that the project was at a standstill as deserted machinery on site could be seen with the gravel road also in a devastating state.

Information revealed then indicated that there had been issues of mining rights for aggregates, availability of structural engineers and manpower and a criteria for awarding tender to the specific company when the contract was terminated.

In 2016, as part of the ESP projects, government funded the 25 kilometres (Km) road project to link Tshesebe and Masunga.

Construction of the road, which also connects some of the villages within the district, commenced early in 2016 and was scheduled to be completed within 18 months.

The company had done nothing when their contract was terminated with allegations that it never had the capacity to carry out the project in the first place.

The major ESP project had ultimately robbed a lot of people potential employment when it succumbed to termination.

It was then that the government restarted the tendering process.

The project was awarded to Bango Trading Company and Zebra Construction in a joint venture at a value of P319 Million Pula.

However, information reaching this publication from the Ministry of Transport and Communications confirms that indeed there are no current works carried out on the Tshesebe Masunga road.

Responding to a questionnaire sent to them by this publication through their Public Relations Officer Doreen Moapare, the Ministry indicated that the Tshesebe-Masunga road project is before the courts therefore their response is limited by such a pending outcome.

“As a background the project had been awarded to Bash Carriers at a contract sum of P400, 044,365.68 to begin the works in May 2017 and complete the project in January 2019. Scopes of works included 51.2km main road inclusive of seven access roads. Due to non-performance, Bash Carriers contract was terminated on the 25th of September 2018. ”

Further, Moapare indicated that upon termination of Bash Carriers, a process began to ensure that the development project completes.

Five companies went for a selective tendering bid which she listed as; Lobkom Investments (Pty) Ltd, Landmark (Pty) Ltd and Truck Hire (Pty) Ltd Joint venture, ACE /Excavator Hire (Pty) Ltd and Asphalt Botswana (Pty) Ltd Joint venture, Cul De Sac, Bango Trading and Zebra Construction Joint venture.

“Some companies have since queried the results of the tendering adjudication landing the issue in the courts. We are currently awaiting a ruling expected in February/March 2021, and this will determine the course of action thereafter,” concluded Moapare.

At one point last year, reports indicated that Bango Trading Construction Company had faced raiding by the Directorate on Intelligence and Security, Botswana Police and Botswana Unified Revenue Services, with allegations that there was an emerging pattern targeting overscheduled construction companies with powerful political connections.

Bango Trading Managing Director, Moffat James, was reported to have had close links to former DIS Director Isaac Seabelo Kgosi. Bango Trading and Estate Construction Company which has obtained close to P 1, 5 billion government contracts under former President Lt Gen Ian Khama has been the subject of a parliamentary probe due to the many government contracts awarded to them.

Continue Reading

News

Gov’t shy to shame failing ministers

22nd February 2021
Morwaeng

Minister of Presidential Affairs, Governance and Public Administration, Kabo Morwaeng together with Permanent Secretary to the President (PSP) Elias Magosi, this week refused to name and shame the worst performing Ministries and to disclose the best performing Ministries since beginning of 12th parliament including the main reasons for underperformance.

Of late there have been a litany of complaints from both ends of the aisle with cabinet members accused of providing parliament with unsatisfactory responses to the questions posed. In fact for some Botswana Democratic Party (BDP) backbenchers a meeting with the ministers and party leadership is overdue to address their complaints. Jwaneng-Mabutsane MP, Mephato Reatile is also not happy with ministers’ performance.

This content is locked

Login To Unlock The Content!

Continue Reading

News

Bokamoso, Gov’t in P10M womb removal suit

22nd February 2021
Bokamoso

Bokamoso Private Hospital is battling a P10 million legal suit for a botched fibroids operation which resulted in a woman losing an entire womb and her prospects of bearing children left at zero.

The same suit has also befallen the Attorney General of Botswana who is representing the Ministry of Health and Wellness for their contributory negligence of having the unlawful removal of a patient, Goitsemang Magetse’s womb.

According to the court papers, Magetse says that sometimes in November 2019, she was diagnosed with fibroids at Marina Hospital where upon she was referred to Bokamoso Private Hospital to schedule an appointment for an operation to remove the fibroids, which she did.

Magetse continues that at the instance of one Dr Li Wang, the surgeon who performed the operation, and unknown to her, an operation to remove her whole womb was conducted instead.
According to Magetse, it was only through a Marina Hospital regular check-up that she got to learn that her whole womb has been removed.

“At the while she was under the belief that only her fibroids have been removed. By doing so, the hospital has subjected itself to some serious delictual liability in that it performed a serious and life changing operation on patient who was under the belief that she was doing a completely different operation altogether. It thus came as a shock when our client learnt that her womb had been removed, without her consent,” said Magetse’s legal representatives, Kanjabanga and Associates in their summons.

The letter further says, “this is an infringement of our client‘s rights and this infringement has dire consequences on her to the extent that she can never bear children again”. ‘It is our instruction therefore, to claim as we hereby do, damages in the sum of BWP 10,000,000 (ten million Pula) for unlawful removal of client’s womb,” reads Kanjabanga Attorneys’ papers. The defendants are yet to respond to the plaintiff’s papers.

What are fibroids?

Fibroids are tumors made of smooth muscle cells and fibrous connective tissue. They develop in the uterus. It is estimated that 70 to 80 percent of women will develop fibroids in their lifetime — however, not everyone will develop symptoms or require treatment.

The most important characteristic of fibroids is that they’re almost always benign, or noncancerous. That said, some fibroids begin as cancer — but benign fibroids can’t become cancer. Cancerous fibroids are very rare. Because of this fact, it’s reasonable for women without symptoms to opt for observation rather than treatment.

Studies show that fibroids grow at different rates, even when a woman has more than one. They can range from the size of a pea to (occasionally) the size of a watermelon. Even if fibroids grow that large, we offer timely and effective treatment to provide relief.

Continue Reading

News

Masisi warned against a sinking Botswana

22nd February 2021
Ndaba GAolatlhe

The Alliance for Progressives (AP) President Ndaba Gaolathe has said that despite major accolades that Botswana continues to receive internationally with regard to the state of economy, the prospects for the future are imperilled.

Delivering his party Annual Policy Statement on Thursday, Gaolathe indicated that Botswana is in a state of do or die, and that the country’s economy is on a sick bed. With a major concern for poverty, Gaolathe pointed out that almost half of Botswana’s people are ravaged by or are about to sink into poverty.  “Our young people have lost the fire to dream about what they could become,” he said.

This content is locked

Login To Unlock The Content!

Continue Reading
Do NOT follow this link or you will be banned from the site!