Connect with us
Advertisement
[spt-posts-ticker]
Friday, 19 April 2024

BPC: It will take 3 years to Fix Morupule B

ENJOYING WATER AT THE TOP TABLE: Minister of Minerals, Energy and water Resources, Kitso Mokaila, BPC CEO, Jacob Raleru and MEWR permanent secretary briefed the nation on energy and water crisis in the country.

It is going to take a while before the future of embattled Botswana Power Corporation (BPC) multi-billion pula mega project Morupule B Power station is known.


The BPC Chief Executive Officer, Jacob Raleru revealed this week that it will take 2-3 years to “fix all what needs to be fixed” at Morupule B. The power plant has failed to produce to full capacity.


“We start procuring what is needed to fix the problems at the plant and it’s going to take two to three years to fix all the problems at the plant,” said Raleru.


This is despite the Minister Kitso Mokaila having gone on record several times stating that the project would be complete in previous years but the deadlines were delayed.


Raleru said that frequent breakdowns of boilers persist and currently the power station is running on 3 units with a power deficit. The units are only producing 310 megawatts (mw) while the whole station is expected to be generating a capacity of 600 mw with each unit churning out 150mw.


The Morupule B plant was initially constructed by China National Electric Equipment Corporation (CNEEC) whose contract was later terminated by government following a dispute of not meeting up contractual obligations, and it was replaced by a German company named STEAG Energy Services which was roped in to assist detect problems created by CNEEC and fix them an effort that is yet to be fully fulfilled.


However Raleru said to alleviate the current problems interim measures have been put in place. He dismissed ongoing rumors that the plant could explode at anytime saying Protection devices are working and periodic inspections of the plant are conducted.


“There is no likelihood of Morupule B exploding,” said Raleru.


He said BPC has regular interactions with African Development Bank (AFDB) and the World Bank (WB) on the way forward.


Of late the country has been experiencing serious power outages following power generation constraints at Eskom. BPC is now short of 150 MW of electricity, following the Morupule B capacity being greatly affected by the South African corporation.


Addressing the media during the same press conference minister Mokaila said Batswana need to understand that Power shortages are not only a Botswana problem but a regional problem.


“There is a general energy deficiency it’s not all about Morupule B,” said Mokaila.


He added that only a quarter of the plant has been affected, and not the whole plant, hence the government can’t do away with whole plant.


He dismissed reports that the P11 billion that was budgeted for the whole plant went to waste. Out of the P11 billion, P3 billion was used to put up the transmission line and water while less than the budgeted P8 billion was used for the construction of Morupule B.


Mokaila said they have strategies in place to deal with the situation. He said his ministry is planning to bring stability at the plant as well as replace and redesign the boilers, which is a long-term plan.


He said all things being equal they are expecting another unit on board by the end of the year.


Regarding the ongoing load shedding and the deal Botswana has with Eskom, Mokaila said Botswana has a non-firm agreement. The agreement allows South Africa to withdraw their power supply anytime if need arises.


Mokaila said plans are underway to ensure that next year Morupule A will be churning out 90 megawatts as well as the 35 megawatts expected to be generated by the Diesel plant by end of July 2016. He said they want the 90 megawatt plant from Orapa to use diesel.


He said plans are underway to change the business model to allow independent power producers to come on board.


Mokaila urged Batswana to be very cooperative by switching off geysers.

Continue Reading

Business

LLR transforms from Company to Group reporting

9th April 2024

Botswana Stock Exchange listed diversified real estate company, Letlole La Rona Limited (“LLR” or “the Company” or “the Group”), posted its first set of group financial statements which comprise the Company and Group consolidated accounts, which show strong financial performance for the six months ended 31 December 2023, with improvements across all key metrics.

The Company commenced the financial year with the appointment of a Deputy Chairperson, Mr Mooketsi Maphane, in order to bolster its governance and enhance leadership continuity through the development of a Board and Executive Management Succession Plan.

At operational level, LLR increased its shareholding in Railpark Mall from 32.79% to 57.79% and proudly took over the management of this prime asset.

The CEO of LLR, Ms Kamogelo Mowaneng commented “During the period under review, our portfolio continued to perform strongly, with improvements across all key metrics as a result of our ongoing focus on portfolio growth and optimisation.

“We are pleased to report a successful first half of the 2024 financial year, where we managed to not only grow the portfolio through strategic acquisitions and value accretive refurbishments but also recycled capital through the disposal of Moedi House as well as the ongoing sale of section titles at Red Square Apartments. The acquisition of an additional 25% stake in JTTM Properties significantly uplifted the value of our investment portfolio to P2.0 billion at a Group level. Our investment portfolio was further differentiated by the quality of our tenant base, as demonstrated by above market occupancy levels of 99.15% and strong collections of above 100% for the period”.

The growth in contractual revenue of 9% from the prior year’s P48.0 million to the current year P52.2 million, increased income from Railpark Mall, coupled with high collection rates, has enabled the company to declare a distribution of 9.11 thebe per linked unit, which is in line with the prior year.

 

In line with its strategic pillars of ‘Streamlined and Expanded Botswana Portfolio’ as well as ‘Quality African Assets’, the Group continuously monitors the performance of its investments to ensure that they meet the targeted returns.

“The Group continues to explore yield accretive opportunities for balance sheet growth and funding options that can be deployed to finance that growth” further commented the CEO of LLR Ms Kamogelo Mowaneng.

Ms Mowaneng further thanked the Group’s stakeholders for their continued support and stated that they look forward to unlocking further value in the Group.

 

Continue Reading

Business

Botswana’s Electricity Generation Dips 26.4%

9th April 2024

The Botswana Power Corporation (BPC) has reported a significant decrease in electricity generation for the fourth quarter of 2023, with output plummeting by 26.4%. This decline is primarily attributed to operational difficulties at the Morupule B power plant, as per the latest Botswana Index of Electricity Generation (IEG) released recently.

Local electricity production saw a drastic reduction, falling from 889,535 MWH in the third quarter of 2023 to 654,312 MWH in the period under review. This substantial decrease is largely due to the operational challenges at the Morupule B power plant. Consequently, the need for imported electricity surged by 35.6% (136,243 MWH) from 382,426 MWH in the third quarter to 518,669 MWH in the fourth quarter. This increase was necessitated by the need to compensate for the shortfall in locally generated electricity.

Zambia Electricity Supply Corporation Limited (ZESCO) was the principal supplier of imported electricity, accounting for 43.1% of total electricity imports during the fourth quarter of 2023. Eskom followed with 21.8%, while the remaining 12.1, 10.3, 8.6, and 4.2% were sourced from Electricidade de Mozambique (EDM), Southern African Power Pool (SAPP), Nampower, and Cross-border electricity markets, respectively. Cross-border electricity markets involve the supply of electricity to towns and villages along the border from neighboring countries such as Namibia and Zambia.

Distributed electricity exhibited a decrease of 7.8% (98,980 MWH), dropping from 1,271,961 MWH in the third quarter of 2023 to 1,172,981 MWH in the review quarter.

Electricity generated locally contributed 55.8% to the electricity distributed during the fourth quarter of 2023, a decrease from the 74.5% contribution in the same quarter of the previous year. This signifies a decrease of 18.7 percentage points. The quarter-on-quarter comparison shows that the contribution of locally generated electricity to the distributed electricity fell by 14.2 percentage points, from 69.9% in the third quarter of 2023 to 55.8% in the fourth quarter. The Morupule A and B power stations accounted for 90.4% of the electricity generated during the fourth quarter of 2023, while Matshelagabedi and Orapa emergency power plants contributed the remaining 5.9 and 3.7% respectively.

The year-on-year analysis reveals some improvement in local electricity generation. The year-on-year perspective shows that the amount of distributed electricity increased by 8.2% (88,781 MWH), from 1,084,200 MWH in the fourth quarter of 2022 to 1,172,981 MWH in the current quarter. The trend of the Index of Electricity Generation from the first quarter of 2013 to the fourth quarter of 2023 indicates an improvement in local electricity generation, despite fluctuations.

The year-on-year analysis also reveals a downward trend in the physical volume of imported electricity. The trend in the physical volume of imported electricity from the first quarter of 2013 to the fourth quarter of 2023 shows a downward trend, indicating the country’s continued effort to generate adequate electricity to meet domestic demand, has led to the decreased reliance on electricity imports.

In response to the need to increase local generation and reduce power imports, the government has initiated a new National Energy Policy. This policy is aimed at guiding the management and development of Botswana’s energy sector and encouraging investment in new and renewable energy. In the policy document, Minister of Mineral Resources, Green Technology and Energy Security Lefoko Moagi stated that the policy aims to transform Botswana from being a net energy importer to a self-sufficient nation with surplus energy for export into the region. Moagi expressed confidence that Botswana has the potential to achieve self-sufficiency in electric power supply, given the country’s readily available energy resources such as coal and renewable sources.

Continue Reading

Business

MMG acquires Khoemacau in a transaction valued at P23Bn

9th April 2024

MMG Limited, the Hong Kong-based mining company specializing in base metals, has successfully concluded the acquisition of Khoemacau Copper Mine, a state-of-the-art, world-class copper asset nestled in the northwest of Botswana.

On Monday, MMG announced that the acquisition of Khoemacau Mine in Botswana was finalized on 22nd March 2024. “This acquisition enriches the company’s portfolio with a top-tier, transformative growth project and signifies a monumental milestone in the Company’s journey,” MMG communicated in an official statement published on the Hong Kong Stock Exchange.

Upon completion of the acquisition, MMG remitted to the Sellers an Aggregate Consideration of approximately US$1,734,657,000 (over P23 billion), a sum subject to potential adjustments post-Completion.

In addition to the Aggregate Consideration, MMG, in accordance with the Agreement, advanced an aggregate amount of approximately US$348,580,000 (over P4.5 billion) as the Aggregate Debt Settlement Amount, to settle certain debt balances of the Target Group (Cuprous Capital/Khoemacau).

On November 21, 2023, Khoemacau announced that the shareholders of its parent company [Cuprous Capital] had agreed to sell 100% of their interests to MMG Limited.

MMG is a global resources company that mines, explores, and develops copper and other base metals projects on four continents. The company is headquartered in Melbourne, Australia, and has a significant shareholder, China Minmetals Corporation, which is China’s largest metals and minerals group owned by the Government of the People’s Republic of China.

On December 22, 2023, Khoemacau Copper Mining (Pty) Ltd received the approval from the Minister of Minerals and Energy of Botswana regarding the transfer of a controlling interest in the Project Licenses and Prospecting Licenses associated with the Khoemacau Copper Mine, a result of the Acquisition.

 

The Botswana Competition & Consumer Authority (CCA) on January 29, 2024, notified the market that it had given its approval for the takeover of Khoemacau Copper Mining by MMG Limited.

On January 29, 2024, the CCA issued a merger decision to the market, stating that after conducting all necessary assessments, it was ready to proceed.

The Competition Authority affirmed that the structure of the relevant market would not significantly change upon implementation of the proposed merger as the proposed transaction is not likely to result in a substantial lessening of competition, nor endanger the continuity of service in the market of mining of copper and silver ores and the production, and sale or supply of copper concentrate in Botswana.

Furthermore, the CCA stated that the proposed merger would not have any negative impact on public interest matters in Botswana as per the provisions of section 52(2) of the Competition Act 2018.

Earlier this month, Minister of Minerals & Energy, Lefoko Maxwell Moagi, informed parliament that his Ministry was endorsing the Khoemacau acquisition by MMG Limited. He noted that not only was the company acquiring the existing operation but also committing to an expansion program that would cost over $700 million to double production, create more jobs for Batswana, and increase taxes and royalties paid to the Government.

Continue Reading