Connect with us
Advertisement

Four projects in 2 years, zero delivery

Alindo Engineering and General Maintenance (Pty) Ltd is a very lucky company indeed. The company keeps on getting jobs with the Department of Technical Services (DTS) but the company rarely ever complete jobs. In the last three years they have been given jobs to the tune of P78 million and only one of the four projects the company was awarded is near completion.


Alindo Engineering is owned by aspiring Botswana Democratic Party (BDP) treasurer. The project completion for the projects stands at 25% (two years overdue for completion) – 90% (two years overdue for completion) – 3.5% (behind schedule by seven months) – and 100 % (final report yet to be handed over).


Pressure from the Public Accounts Committee (PAC) has forced the DTS to instruct government lawyers to demand over P6 million owed to Government from the first project. Two other projects have also been red flagged for termination because of poor implementation albeit he has been paid million as part payment for the undelivered projects. According to records, Alindo Engineering keeps on getting jobs despite its record of failing to deliver projects.


The 25% progress after three years


He was given a job for the construction of 4No. Double Storey 4 units staff houses for Maiteko Junior secondary School at the tune of P18 894 333. 47 on 31 March 2014 and he was expected to complete the projected on 05-01-2015 and later date was revised to 19-01-2015. The project as things stand is still at 25 percent completion despite the fact that he has already been paid P8 933, 077.59.


Explaining the back and forth, DTS writes: “The contractor abandoned the project since September 2015 to date. He owes the Government P6, 188, 884.01 which accrued from rejected works and unpaid mobilization. On 2nd May 2017 DTS wrote to the contractor to state how he is going to pay the Government the money he is due to pay. He wrote back on 26th May 2017 stating that the money will be paid by a proposed assignee.


The mobilization was waived to stabilise the contractor’s cash flow problems with a hope the contractor will complete the project. This decision was guided by FIDIC, (The International Federation of Consulting Engineers) clause 3.5 which state that “the conditions provide that the Engineer shall proceed to agree or determine any matter, the Engineer shall consult with each party in an endeavor to reach agreement. If agreement is not achieved, the Engineer shall make a fair determination in accordance with the contract, taking due regard of all relevant circumstances.” Attorney General’s Chambers will be contacted to assist in recovering the money owed.


The only completed project


Alindo Engineering and General Maintenance Pty Ltd also worked on the construction of staff houses at Marakanelo JSS at Ncojane. The contract sum is P10, 714, 659.20 and the contractor was paid P5, 077, 897.25. The project was awarded on 10th April 2014 and was expected to be completed on 05 December 2014 but the completion date was later revised to 25 March 2015. While the status of the project is that it has been completed, the briefing notes indicate that the final account for the project will be concluded and finalized in the second quarter of 2017/2018.


Stuck at 90% progress for four years!


On  the 11th November 2013, he was given a project to refurbish the Curriculum Development Building, in Gaborone at the tune of  P5, 932, 710.93 and he was paid P5, 422, 627.67. He was to complete the project on 28 April 2014 and the project completion date was revised to 30 August 2016. Today the project progress stands at 90 percent completion.


This is howDTS explains this situation: “The contractor is struggling to complete the contract. He was a written a letter of Notice to terminate on 4th July 2015 which he replied on 9th July 2015 by opting for mutual termination. He was invited for a meeting on 31 August 2015 to discuss mutual termination but never attended or replied the invitation letter.


On 6th April 2017 he was written a letter of Notice to Terminate and replied on 26th April 2017, he further wrote on 23 May 2017 requesting for inspection and subsequent handover of the project. On the 13th June 2017 DTS team visited the project for final inspection, but on arrival on site they noticed that contractor did not finish the works. He further pleaded that he will complete by end of June 2017. After June 2017 if the work is not complete, contract will be terminated.”


Shocking 3.5% progress in six months


On 1st December 2016 the same contractor was awarded a job to construct 9No 2beds Double Storey and 2No LA3 staff houses for Moeding College at Otse at the value of P43, 000, 062. 71 and was paid P6, 945, 543.55. The expected completion date for the project is 31st December 2017 and at the moment the project is at 3.5 percent completion.


And the DTS explanation: “DTS wrote a letter on 15th May 2017 requesting to meet the Contractor and Client (Moeding Colege) on the 22nd May 2017 top discuss poor progress of the project. After holding the meeting on 22nd May 2017 Moeding Colege wrote to the contractor requesting for recovery plan or catch up plan from the contractor. On the 9th June 2017 the contractor wrote proposing to subcontract works. On the 13th June 2017 DTS responded seeking clarity pertaining to the contractor’s proposal.

On the 14th June 2017 DTS team visited the site and observed that the progress on site is still at 3.5 percent. DTS has visited the site again and still found that the progress is still at 3.5 percent. This poor performance of the contractor has been referred to the UCCSA Board of Governors so that appropriate action on contractual obligations and possible act on non-performance by the contractor.”

Continue Reading

News

 Zakhem vindicated

15th September 2021
Zakhem

Botswana Football Association (BFA) leadership appears to be bowing down to Nicolas Zakhem’s football pressure. The development comes to the open roughly 24 hours after the Gaborone United director publicly labelled Maclean Letshwiti and his committee failures for deciding to chop five premier league clubs under the pretext of club licensing disqualification.

As early as Wednesday noon, the BFA emergency committee met with one agenda item to discuss the possibility of reinstating the clubs. This publication gathers that the committee saw it fit to pardon the five clubs without entertaining a second thought. The committee even invited the clubs to the meeting, sources say.

Late last month, the five teams were disqualified from playing in the premier league, pending the appeal outcome. The teams are Notwane, Extension Gunners, BR Highlanders, Mogoditshane Fighters, together with Gilport Lions. The immediate decision by BFA follows what Zakhem had said and advised that it was wrong to chop clubs given the COVID-19 situation in the country.

Unbeknownst to BFA leadership, observers stress that Zakhem exerted public pressure and influenced them to change tone without asking. At the meeting, BFA president Maclean Letshwiti, his vices, Marshlow Motlogelwa and Masego Ntshingane, Aryl Ralebala, the Botswana Football League (BFL) chairman, together with Alec Fela, an ordinary member in the now stubborn NEC.

However, the reactive move by the association to reinstate the clubs is highly welcomed in certain quarters, but it also appears to have left a permanent scar, especially at BFL. As things stand, the general feeling on the ground is to oust chairman Ralebala for failing to defend these clubs before the eyes of President Letshwiti.

This publication has intercepted an ongoing petition to unseat Ralebala and his deputies from the BFL board. Strange enough, the signed petition has thus far attracted clubs with household influence in the league itself. GU, Township Rollers, Notwane, Extension Gunners, Police XI are some clubs that have already appended their signatures to have Ralebala removed.

The big clubs are believed to fighting for principle and demand fair governance at BFL. The reality is that these clubs command a large following, and sponsors can always have a say based on their presence.

When approached for clarity, Ralebala said he could not comment on allegations or issues that lack substance. He concedes that he has heard about the rolling petition but is yet to lay his eyes on it.
“I have heard about the petition, but I don’t know where it is coming from. I think it is best you ask those who have signed it. My focus is to commence the league and make sure everything is on point,” said Ralebala.

Football observers state that Ralebala, together with Letshwiti, are now faced with a dilemma. Reports coming from Lekidi Football Centre, although yet to be fabricated, are that the big guns lead others to form a parallel structure where they will play on their league. The clubs are angry at their chairman for taking many of the instructions from the BFA boss, and already a general melee is gathering traction that the two must resign as football has lost direction.

Zakhem says, although he supported Letshwiti, he has a sense of duty to stand for the truth. “I knew I supported Letshwiti and his troops, but you see, these guys have lost direction. I have long advised them that chopping clubs like this will cause confusion and delay progress, but they cannot listen. Letshwiti gave BFL autonomy, but I do not know why he is still interfering,” Zakhem said.

Continue Reading

News

The untold brighter side of the P100bn case fall

15th September 2021
President Dr Mokgweetsi Masisi

You may, by now, have heard about the dark side of the high profile P100 billion case, but wait, there is also the brighter side. Staff Writer AUBREY LUTE explores the positives accruing from the fall of the country’s biggest financial ‘scam-dal’.

A chance to fix the country’s financial record

They have not publicly been saying it, but the state agencies and the President, Dr Mokgweetsi Masisi, have been at pains to explain and rationalise how an amount almost equal to the country’s GPD left the central bank.

Many insiders attributed the country‘s troubled financial status to the case, including the grey-listing, non-compliance and identified deficiencies, some of which were hitting citizens around the globe. Botswana was in 2018 taken aback by FATF news that the country has been listed alongside countries that do not comply with (AML/CFT). The European Union Commission later flagged Botswana in March 2019 for lacking strategic deficiencies in AML/CFT regulations.

A chance to restore the dignity of the law enforcement arms

The case, without a doubt, was a distraction object on the law enforcement agencies, which spent a chunk of their time bickering and finger-pointing. A leaked audio recording exposing the explosive meeting of the law enforcement arms of government, being the Intelligence Services, Corruption and Economic Crimes agency, and the Prosecutions division summed it all.

The case presented a monumental crisis threatening the core of their being. Following these developments, the Presidency, clearly under the influence of a tripartite member, took a spine-chilling decision to disband the DCEC, a move that was saved by the organisation’s founding director- Tymon Katlholo’s bold protest.

The DPP, the Police, and the DCEC staff were used in the process to carry out bizarre instructions, some of which left the state with an egg on its face. Mistrust and backstabbing were the order of the day within the law enforcement agencies, and the P100 billion case was to blame. “Some badly wanted the plot executed while the other side badly wanted it to end to restore sanity,” an insider says.

The source further adds that “if the case did not end soon, it was going to end a lot of people’s relationships and careers because those who refused to carry the insane instructions were seen as sympathisers to former President Ian Khama.” With the case having fallen, these agencies can reflect, reconcile and go back to work.

A chance to fix diplomatic relations…

It was not only South Africa that was accused of Sabotaging Botswana’s prosecutorial goal. The state also accused several countries of refusing or delaying to assist in the process. Of all the nations, only South Africa has decided to take Botswana to task, perhaps on its proximity to Botswana. Others long ignored Botswana’s requests for assistance to the frustration of former DPP deputy director who repeatedly told the courts that they were struggling to get responses from the international community. With the case having fallen, Botswana may get a chance to face her actions, apologise and rectify the promise that lessons have been learnt.

Pressure off the shoulders of those who have to account…

The case did not only affect the law enforcement agencies. All the stakeholders were put in the spotlight to provide answers. The first to bolt out of the circle was the central bank, Moses Pelaelo, who, like DCEC director-general, long declared the case a scam. He told the world that his books were in order and that no money was missing risking his high-paying job.

According to insiders, his superiors, the then Minister of Finance and Development Planning – Dr Matsheka and his subordinate, Dr Wildfred Mandlebe, were only whispering, without success, to the Gods that there is no money missing.

So concerned and under pressure was Dr Sethibe- then the head of the Financial Intelligence Agency- who, like his Ministry supervisors, was engaging in silent screams to warn the powers that be, all in vain. He later jumped the ship to his former employer, the University of Botswana, allegedly to protect his name and career.

At the time of the fall of the case, the DIS and the DPP were at advanced plans to higher American to come and probe the Bank of Botswana’s servers in a move that bankers feared could compromise them further.

The case was bleeding the country’s coffers…

Had it not ended, the case was likely to end up ‘genuinely’ costing the country P100 billion Pula duo to its complexity and challenges. Insiders say sources who had sold the law enforcement agencies some falsified documents were paid handsomely.

Moreover, investigations were costly as they involved the international community and frequent travelling. “We are told there was also motivation for some officers to act abysmally and out of their way,” an insider said.

Lessons leant for public officers…

Public officers are often duty-bound to obey superiors instructions, no matter how irrational. The case was an eye-opener to many public officers that principle pays in the discharge of one’s duty at all times. The professional careers of the P100 billion case conspirators are currently in shambles. And as expected, the influencers, if at all there any, are nowhere to be seen.

Continue Reading

News

Botswana could exit FATF “greylisting” in October 

15th September 2021
President Dr Masisi & Minister of Finance and Economic Development Peggy Serame

Botswana remains on the grey list of the Financial Action Task Force (FATF) and the “black list” of the European Union, a status quo that highlights the country as one of the high-risk jurisdictions to deal with money.

The far-reaching implications of these listings is a compromised Foreign Direct Investment drive for Botswana. In particular, these listings mean investors now have to exercise some caution and restrain when thinking about putting their money in Botswana. On Tuesday, Minister of Finance and Economic Development Peggy Serame said that Botswana could see itself out of the “undesirable listing” by October this year.

Serame called for united and concerted efforts towards liberating Botswana out of this financial noncompliance tag. She said the delisting could be archived by concerted efforts from all stakeholders: players in the financial services sector, non-financial services businesses, regulators, and every individual who deals with transactions.

Botswana is a founding member of the Eastern and Southern Africa Anti-Money Laundering Group (ESAAMLG). This regional body subscribes to the Financial Action Task Force (FATF) to combat money laundering and financing of terrorism and proliferation.

One of the membership obligations to ESAAMLG is for Botswana to be peer-reviewed by the other Member States and other international bodies like the World Bank, IMF or FATF.
The most recent assessment for Botswana to gauge compliance with the FATF standards was conducted by ESAAMLG in 2016 and culminated with publishing the Mutual Evaluation Report (MER) in 2017.

Following the discussion and adoption by the Task Force and approval of the MER by the Council of Ministers, the country was placed under enhanced follow-up.  This led to a one (1) year observation period in which the country was expected to improve its technical compliance (legislative framework) by correcting the deficiencies identified in the MER.

After one year, in October 2018, the Task Force decided that the country was not taking sufficient steps to implement the recommendations made by the assessors in the MER.  The Task Force recommended that Botswana be referred to the International Cooperation Review Group (ICRG) for monitoring and potential listing often referred to as the ‘FATF greylisting”.

Following the FATF greylisting, the EU placed Botswana on its list of high-risk third countries, often referred to as the ‘black list.’ In 2018, Botswana and FATF agreed to an Action Plan that had six items with several timelines. In terms of Risk and coordination, Botswana was told to develop and implement a risk-based comprehensive national AML/CFT strategy, assess the risks associated with legal persons, legal arrangements, and NPOs, and operationalize the modernized company registry to obtain and maintain essential information and Ultimate Beneficial Ownership information.

Botswana was further advised to enhance the capacity of the supervisory staff, including by developing risk-based supervision manuals and providing adequate training, implement risk-based AML/CFT supervision and impose sanctions against violations.

Furthermore, Botswana was instructed to improve analysis and dissemination of financial intelligence by the Financial Intelligence Unit, including operationalizing an online Suspicious Transactions Report filing platform and prioritizing high-risk predicate crimes, and enhancing the use of financial intelligence among the relevant law enforcement agencies.

Regarding terrorism financing investigation, Botswana was instructed to develop and implement a Counter Financing of Terrorism Strategy, operationalize the Counter-Terrorism Analysis and Fusion Centre, and ensure the Terrorism Financing investigation capacity of the law enforcement agencies.

In 2018, the 11th Parliament passed 25 pieces and, later, six others related to AML/CFT/CFP. At the just ended Parliamentary session of the 12th Parliament, lawmakers passed the Financial Intelligence (Amendment) Act to address the definition of beneficial ownership.

Cabinet approved the National AML/CFT/CFP Strategy of 2019-2024 in October 2019. At the June 2021 FATF Plenary meetings, the FATF made the initial determination that Botswana had substantially addressed the Action Plan and that this warranted an on-site assessment to verify that the implementation of Botswana’s AML/CFT/CFP reforms is in place and is being sustained.
Furthermore, an assessment was to be instituted to check if the necessary political commitment remains to sustain implementation in the future.

Serame said in a televised press briefing that Botswana’s exit from the FATF grey list and the EU black list would be determined by the outcome of the on-site assessment, which will be discussed at the FATF Plenary in October 2021.

She revealed that the Botswana delegation attended the Eastern and Southern Africa Anti-Money Laundering Group 42nd Task Force of Senior Officials meeting from the 26th August to the 6th September 2021, followed by the Council of Ministers on the 7th September 2021.

She told the media that at these meetings, Botswana was commended for making progress in complying with the FATF standards by addressing deficiencies in her AML/CFT/CFP framework.
“We are making all these efforts of complying with the FATF standards so that we guard against our financial system being used for money laundering, terrorism financing and proliferation financing,” she said.

“We are hopeful that at the October 2021 FATF Plenary meetings, the outcome of the on-site visit undertaken by the FATF in August 2021 will bear positive results, leading to Botswana being delisted from the FATF greylisting,” she said. However, Minister Serame called on all stakeholders to support the government to remove Botswana from the greylisting.

“As Government continues its efforts of putting in place the necessary legislative and institutional framework, due diligence must be exercised by all institutions, including the ordinary Motswana, so that no one is found dealing with financiers whose credibility is wanting,” she said.

The minister reiterated that all players in the financial services sector had a role to play: “It is important that where unsolicited funds are offered, the individual or entity so receiving the offer must ensure that the funds being offered are not associated with unlawful acts. If we are not diligent, criminals may use unsuspecting people and entities to launder proceeds of crime.”

She reiterated that the government is committed to doing all within its power to remove the country from the FATF “grey list” and the EU “black list”. However, she noted that to achieve that requires the cooperation and assistance of financial institutions, designated non-financial businesses and professions and individuals to ensure full compliance with AML/CFT/CFP rules and regulations.

“These efforts will not only assist us to be removed from these mentioned lists but are for the benefit of our country to maintain a high standard of financial prudence and an economy which genuine investors can have the confidence to invest in,” Serame explained.

Continue Reading
Do NOT follow this link or you will be banned from the site!