Connect with us
Advertisement

Zakhem to get P90 million windfall as Ministry ‘surrenders’

ZAC Construction may soon smile all the way to the bank after the Ministry of Transport and Communications caved in after the contractor of Charleshill-Ncojane road lodged a dispute with the Dispute Adjudication Board (DAB) demanding compensation.

If successful ZAC Construction will get a possible P70 million award and another P20 million from an initial claim against the Ministry of Transport and Communications. Reports suggest that while ZAC has made compelling submissions before the Board, the Ministry is somewhat cold and submissive. An attempt by Department of Roads to submit a constructive written response was denied while ZAC Construction was allowed to supplement its earlier filing.


Nicholas Zakhem’s company has made three claims before the Dispute Adjudication Board, with the first dealing with “Costs for the initial delay”. In its response the Roads Department notes that “If and only if the DAB finds that the Contractor’s referral has merit, in order to save time the Employer has reviewed the Contractor’s computation of costs and confirms it is correct. “ Before stating as captured above the Department confirms that the Contractor (ZAC) has agreed to the extension of time granted and that this is not in dispute.

“The point of principle is should the Contractor be paid,” they write, while also stating that the Engineer, who they have since fired, determined the Contractor has no entitlement to compensation. In the second claim, ZAC Construction is querying the “Change to vertical alignment”. The contract is a design and construct contract. The Department of Roads notes that “the point of principle regarding claim 2 is whether the Engineer’s instruction to increase the vertical alignment is a variation.” Again, the Ministry states, “If and only if the DAB finds that the Contractor’s calculation of the extension of time and computation of costs and confirms it is correct.”

The third claim deals with the “Pre-collapse treatment. “The point of principle regarding Claim 3 is the Engineer’s time-barring. The Fidic contractual provision for time-barring is covered under clause 20.1. As is the standard response, the Department of Roads writes, “If and only if the DAB finds that the Contractor’s referral has merit, in order to save time the Employer has reviewed the Contractor’s computation of costs and confirms that it is correct.” The DAB is chaired by Mr Jeffrey Bookbinder of Bookbinder Business Law.

COURT BATTLES ONGOING

The dispute around the Charleshill-Ncojane road are also playing themselves out in the courts where the permanent secretary in the Ministry of Transport and Communication, Kabelo Ebineng is compelled to defend his 20 year friendship with businessman Nicholas Zakhem who convinced him to terminate a contract for a Consultant engaged in the construction of the Charles Hill- Ncojane road.

ZAC Construction, whose Managing Director is Zakhem is the contractor in the project. The two parties are throwing jabs of conflict of interest at each other and the permanent secretary has stated that he has even borrowed money from Zakhem, a red flag already observed by the consultant, Bothakga Burrow and other players in the matter. It not clear what the role of the Permanent secretary is in the current claim before the Dispute Adjudication Board and how the members of this Board are appointed because the Ministry had not responded to our questions by the time of going to print.

It is not clear as to whether the dismissed Consultant Engineer will be given a chance to respond to some of the claims made by ZAC Construction because Bothakga was responsible for some of the decisions in question. From the beginning of the project, Zakhem had flatly refused to work with the Consultant, Bothakga Burrow Botswana (BBB) accusing them of being difficult to work with and later alleging conflict of interest on their part – they had tendered for the same project, he said. BBB was awarded the Consultant contract by the PPADB with the Ministry of Transport and Communications as the procuring entity.

As of 16 February 2018 Bothakga Burrow Botswana has dragged the Ministry of Transport and Communications before court accusing it of unlawfully terminating its contract. Ebineng terminated BBB’s contract with effect from 16 February 2018 citing convenience on the part of the Employer or procuring entity. But Bothakga is arguing that the Ministry did not follow the correct procedure when terminating the contract and the Public Procurement and Asset Disposal Board (PPADB) agrees with Bothakga.

Zac Construction was awarded the Charles Hill – Ncojane tender on 26th November 2013 for an amount of P436 279 046. 45 to be completed in 36 months on a design and build basis. In January 2017, sixteen months after commencement of construction Zac or Zakhem complains to the Ministry of Transport citing conflict of interest on the part of the consultant, Bothakga Burrow. His views are such that the consultant has not been properly appointed and he threatens to stop taking instructions from the Consultant and requests that Bothakga Burrow be removed from the project.

Records show that in May 2017, one month after the appointment of Kabelo Ebineng as Permanent Secretary at the Ministry of Transport, Zakhem restarts work after a four week unauthorized stoppage of work, and reconfirms that they will not work with the Consultant, Bothakga Barrow, and again he requested the removal of the Consultant.

What has irked Bothakga Burrow directors before their contract was terminated is that the Permanent Secretary at a meeting held on 19th June 2017 he confirmed that “he and Mr Nicholas Zakhem know each other socially. He mentioned that he has even had the opportunity to borrow money from him because of their relationship and they continue to have a relationship.”  After this meeting Bothakga Burrow requested that Ebineng recuse himself from meeting dealing with the matter but he refused stating that there was no conflict of interest.

During the course of July 2017, construction was suspended by the consultant, because the contractor was no longer accepting project works to be tested, as per the contract, however the Contractor proceeded to construct 12km of road, whose quality could not be vouched for. Ebineng immediately requested Bothakga to withdraw the suspension and he instructed Zac Construction to proceed with construction work unsupervised. Records further show that by September 2017 the Parliamentary Committee on Communications, Works, Transport, and Technology, had visited the project site to understand the challenges on the project.

Shortly thereafter the Contractor on his own volition stopped construction on the project, and demanded to be paid for the 12km of road that he had refused to have tested. The Consultant was asked by the permanent secretary to certify payment for the 12km, and declined to do so without verifying the quality of works in accordance with the contract. Indications are that at some stage the Permanent Secretary to the President, Carter Morupusi intervened and advised that the project be executed in accordance with the signed contracts of all parties. In all meetings, Zac Construction requested that the Consultant be removed as a pre-condition to return to work on the project.

WeekendPost learns that by the end of 2017 the Ministry had paid Zac Construction for the 12km of untested road works; failed to test or verify the quality of the constructed work; acceded to the contractor’s request to remove the Consultant from the project; the permanent secretary has refused to recuse himself from dealing with the matter which he is said to be conflicted; the PPADB had notified him that his position is untenable.  

Ebineng’s defense of his relationship with Zakhem is a simplified one. He states that he knows most of the contractors, engineers, and consultants that deal with his Ministry. He states that most of them he went with them to school, met them at play grounds, socializes with them hence he wonders if he will recuse himself for almost everyone in town. On the other hand allegations of conflict of interest on the part of Bothakga were dismissed by the PPADB but the Ministry through Ebineng held that conflict was inherent.

The two parties are now in court with Bothakga Burrow Botswana pleading with the court to reverse the unlawful decision of the permanent secretary. Bothakga Burrow Botswana’s contract is worth P40 million. Judge Rannowane gave both parties an ear on 16th March 2018 and will deliver judgement next month.

Some in the Ministry are worried that Ebineng’s actions are setting a bad precedent that will have far reaching consequences for the entire construction industry where contractors can pick and choose who they want to supervise them. They also raise a concern for the role of PPADB in awarding and terminating contracts, where government can willfully undermine its own laws and institutions.

Continue Reading

News

No deal was made with Disney World – Tsogwane

16th April 2021
disney-carlifonia-park

President Dr Mokgweetsi Masisi has been touring the entire world since occupying Presidential office in 2018. Few months down the line, he flew to Florida in the United States of America where he landed at the Disney World.

This is the world’s largest entertainment complex opened in 1971, with four theme parks (consisting of Magic Kingdom, Epcot, Disney’s Hollywood Studios, and Disney’s Animal Kingdom).

Upon his return in the country from the fairytale land, Masisi said Botswana struck a partnership with Disney World. The partnership primarily focused on turning the country’s capital, Gaborone, into an international tourism and leisure destination.

“We have struck a partnership with Disney World as a company. They focus on making people happy and bringing tourists. I want tourists in this country. Visa restrictions are out. They will be issued on arrival. I have tasked Minister Makgato’s Ministry to categorize taxis so that there can be value in the taxi industry.

I am very committed to making Gaborone an international venue center and this will bring revenue to our country,” Masisi said at the time. Masisi, has now appointed Makgato as Botswana’s High Commissioner – designate to the Commonwealth of Australia.

However, two years later, there is no sign of Gaborone being turned into a tourism hub. In fact, the partnership Masisi struck with Disney World never emerged. It is now becoming more of a pipeline dream, and politicians are keen to know what really transpired.

In a dramatic turn of events, Masisi’s flanking Minister, Minister for Presidential Affairs, Governance and Public Administration, Kabo Morwaeng, slammed Vice President Slumber Tsogwane with questions on this said ghost partnership, demanding answers on Masisi’s long dead promise.

Vice President Tsogwane told Parliament on Thursday that Masisi was looking for investors to come and do business in Botswana, either in partnership with government or the private sector.

“The President and his delegation engaged in meetings with the management of Disney World to identify opportunities for the company to collaborate with in Botswana. There were a number of opportunities Mr. Speaker for collaboration that were identified to be followed up with by bilateral negotiations with various institutions.

The key area that was identified for collaboration was the implementation of an enhanced customer care training and development akin to that of Disney World.

The Botswana Public Service College was assigned to collaborate with Disney World, to roll out a training programme which will achieve excellent customer service for the public sector in Botswana, Tsogwane said via virtual Parliament.

He further said representatives of Disney World visited Botswana on a fact finding mission in May 2019.

“While in Botswana, the team toured selected sites such as Gaborone bus rank, Tlokweng Boarder post, and Department of Roads, Training and Safety offices amongst others. Following this, Disney World produced a scoping report which detailed training and engagement timelines for consideration by government,” said Tsogwane.

In fulfilment of their procurement requirement, Tsogwane said Disney Institute was requested to submit a proposal based on their scoping report indicating associated cost implications. He said, Disney declined to submit citing that it does not deal directly with government.

“After being advised by their Disney World Board, they therefore advised Botswana government to deal with another company in the United States of America, which according to them does the Disney World way. This never proceeded because our interest was on Disney World and not any other company that point in time.”

As a result, Tsogwane told Parliament that no deal or contract was signed with Disney World. “The issue of easing of restrictions which is part of the question, between any two countries is a matter that is negotiated through diplomatic channels and whenever agreements are reached, proper communication is made. With regard to Visa restrictions between Botswana and the US, Tsogwane says they will continue discussions on how to ease restrictions,” he said on Thursday.

Morwaeng wanted Tsogwane to update Parliament on: Government’s deal with Disney World, the terms of the deal propounded by the President in March 2019; Whether the deal was signed, when it was signed and clear specifics of the deal and its benefits to Botswana tourism; when visa restrictions between the two countries (Botswana and the United States of America) will be eased and visas issued on arrival as per the Disney World deal pronouncement; and If the deal struck with Disney World was not just mere electioneering talk that will never see the light of the day.

Continue Reading

News

Gov’t has no budget for Magosi’s SADC chase

12th April 2021
Elias Magosi

Despite the government of Botswana’s ambition to have one of its own to lead Southern Africa Development Community (SADC) since its establishment in 1980, the Presidency says there is no budget specifically dedicated to the campaign.

The Government has released the name of Permanent Secretary to the President, Elias Mpedi Magosi, as the candidate for the SADC Executive Secretary position. Magosi is expected to face off with Democratic Republic of Congo (DRC) candidate, Faustin Mukela. The position will become vacant in August this year.

However, despite the optimism the Botswana Government has not yet set aside a budget to assist Magosi to win against the seemingly DRC giant. “We all know that the COVID-19 pandemic has negatively affected the country’s ability to effectively fund any new project. This campaign is not an exception. As such, we do not have any budget for the campaign. However, we have so far managed to take advantage of His Excellency the President’s working visits to the neighbouring countries to also carry out the campaigns,” Press Secretary to the President, Batlhalefi Leagajang, explained.

Botswana has housed SADC since the establishment of the then SADCC in 1980, but has never occupied top most leadership positions at the SADC Secretariat.  “We therefore, strongly believe that we should also have an opportunity to contribute to the management of our regional body as it continues to drive the important issues of regional integration industrialization and socio-economic development.

This will also profile Botswana as a strong advocate of regional integration,” he responded to this publication’s questionnaire as to why the Government wants to occupy the plum post. SADC is a Member State driven organization. As such, Leagajang said, needs a well-grounded Executive Secretary with a blend of management and leadership acumen; a transformational leader with political awareness and integrity; private and public sector experience; a deep culture of corporate governance; as well as strategic agility and result-oriented consummate diplomat.

“These are the unique attributes of our candidate,” he said. So far President Mokgweetsi Masisi has visited nine out of 16 SADC member states on a working visit and also taking an opportunity to present to them his candidate.

“The countries have appreciated this effort and we remain hopeful. However, it is important to note that this is a democratic and competitive process which must be respected,” he responded when asked about the reception and assurances from various countries to cast a vote for Magosi.

In 2018, when Pelonomi Venson-Moitoi challenged for the Africa Union (AU) Chairperson, the government appointed former President Festus Mogae to be the campaign leader. Does the Government have anyone apart from Masisi to help with the campaign?

“The campaigns for the candidate are strictly led by the Government of Botswana. Since this is a candidate for Botswana, not just the Government, it will be appreciated if all Batswana, including the media, could also shoulder the responsibility to campaign for the candidate in their own spheres of influence,” Leagajang responded.

While there are sceptics on Magosi winning against the DRC man, the Government is confident and believes that with the unique traits that he possess, Magosi stands a chance. He is said to be a strong advocate of justice and fairness as he has played this role in his current role as PSP and in his previous roles as PS and in the private sector. He has helped individuals and companies to find justice and fairness in most of their dealings with Government.

Magosi is also said to be a proponent of corporate governance and which he has relentlessly pursued in most of his career including in Government and other sectors. A strong believer in following laid down procedures and laws. “He carries a variety of skills as an HR expert with experience in different sectors, a strategist and an Organization development specialist.

His experience and exposure spans government, parastatal, private sector and at regional level as well, thus making him a suitable candidate for the regional role. He has worked with governments, businesses, development partners and politicians and is comfortable navigating through all of them,” Leagajang concluded.

Continue Reading

News

Mzwinila’s P4.3 Billion gamble to keep water flowing

12th April 2021
orth-South-Carrier

The Minister of Land Management, Water and Sanitation Services, Kefentse Mzwinila looked a politician set to shoot the moon as he laid bare his billions of pula development agenda recently in Parliament.

His Ministry’s combined Recurrent and Development Budget Proposals for the 2021/ 2022 Financial Year is pegged at Four Billion, Three Hundred and Sixty – Five Million, two Hundred and Nineteen Thousand, Five Hundred and Sixty Pula (P4, 365, 219, 560). This is a budget 38.3% more than the allocation for the 2020/2021 Financial Year.

Mzwinila preluded his request to parliament with a demonstration that his Ministry has no champagne taste on a beer budget – indicating that his ministry’s expenditure at the end of February 2021P2.111 Billion or 96% of development budget; and P910 million or 90% of the recurrent budget.

Notwithstanding the budget dust, the Minister justified this year’s increase in the Ministry’s total budget. He attributed the escalation to the commencement of major projects under the water sector. These include the implementation of the North South Carrier (NSC) 22.2 covering various sub projects. Mzwinila noted that these are all public value projects which are aimed at improving the lives of Batswana.

Mzwinila’s Ministry has projected that the sum of Nine Hundred and Sixty –Three Million, Nine Hundred and Forty – Seven Thousand, Five Hundred and Sixty Pula (P963, 947, 560) be permitted for the Recurrent Budget and stand part of the 2021 / 2022 Appropriation Bill ( No. 1 of 2021).

“55% of the Recurrent Budget is geared towards the Revenue Support Grant for 12 Land Boards and their subordinate authorities while the sum of P5 Million is allocated to the Real Estate Advisory Council (REAC). The remaining 44% is proposed for the Ministry Departments.”

The sum of Three Billion, Four Hundred and One Million, Two hundred and Seventy –Two Thousand Pula (P3, 401, 272, 000), for the Development Budget was approved and stand part of the same schedule of the appropriation (2021/2022).

When breaking down the Development Budget, Minister Mzwinila noted that Water Supply and Sanitation projects will account for P1.098 Billion to finance the Maun Water and Sanitation project, Molepolole Sanitation projects and the Shakawe Water Treatment Plant Rehabilitation.

With all the implementation bottlenecks troubling several projects in the country, Mzwinila had to satisfy the question of whether his Ministry demonstrated a dire need for the budget with reference to its execution of the budget for the financial year 2020/2021 and its delivery of strategic initiatives and projects?

Mzwinila’s pitch found favour with parliament and his ministry will get an aggregate budget of P3.198 Billion for the 2020/ 2021 Financial Year. Within this allocation, P2.188 Billion is for the Development Budget and P1.010 Billion will cover the Recurrent Budget.

The Minister revealed his strategic interventions for land management, water and sanitation services. Highlighting that efforts by Government to provide serviced residential land to citizens on the waiting list are being hampered by limited resources. He shared that his ministry needs P94 Billion to cover such costs which will directly link to water, sewage, roads, electricity, telecommunications and storm water drainage leading to the allocation of 4 587 plots on un-serviced land.

The minister projected that 22 952 un-serviced residential plots are planned to be allocated in the next financial year. However, there is a trend where allocated land remains fallow and undeveloped which raises misgivings that the requests could have been made on speculative plans.

Mzwinila noted that in the spirit of forging stronger International connections, the Ministry will in June 2021 sign a Memorandum of Understanding on Land matters between Namibia and Botswana with the aim of opening doors to the creation of Dry Ports in the country, facilitate international trade through Walvis Bay Sea Port.

Botswana is already challenged by scarcity of naturally occurring water resources due to the aridity of the country creating persistent water shortages. The type of infrastructure required to improve national water security is a true reflection of intensive investment needed in the water sector The Minister stressed.

“An emerging issue such as the COVID -19 pandemic poses serious challenges as the control of the virus requires reliable water supply. In an effort to mitigate the challenge, the Ministry has undertaken extensive bowsing throughout the country which included the provision of additional capacity for supplementary bowsing to areas with pervasive water shortages, plus an additional forty one (41) un-gazetted settlements.

Operational costs due to bowsing were at an average of P6 Million per month before the COVID-19 pandemic and increased to an unsustainable amount of the order of P13 Million per month, since the beginning of the State of Emergency in April 2020,” the minister shared.

Through the support of a World Bank Loan, the Ministry is implementing several initiatives under the Botswana Emergency Water Security and Efficiency (BEWSE) project. Through BEWSE the Raw Water Pricing and Abstraction Strategy will assess the pricing of water in a manner that enables the provision of water to support new economic development, the strategy is planned to be completed in June 2021.

The Ministry has commenced the development of a long term National Water Security Strategy to improve resilience to climate change impacts. The strategy development entails prioritization of the proposed future mega water transfers such as the Chobe – Zambezi water transfer, the Atlantic Ocean water transfer to Botswana through Namibia and Lesotho – Botswana water transfer.

Following the signing of the tripartite Memorandum of Agreement (MoA) between Botswana, Lesotho and South Africa in November 2017 for the Lesotho –Botswana Water Transfer project, a 24 months contract for a combined prefeasibility and feasibility study for the development of a bankable Lesotho – Botswana Water Transfer project feasibility study was signed and is to be completed in 2022.

One of the Ministry’s famous major water supply projects such as the North South Carrier (NSC) 2.2 has experienced hiccups; having tenders for contract 1 (Masama to Mmamashia Pipeline) and Contract 2 (Mahalapye to Masama Pipeline) cancelled due to budgetary constraints.

Continue Reading
Do NOT follow this link or you will be banned from the site!